Project timeline
The construction of our development at North Warmley will be phased over fourteen years, with houses being built alongside new and enhanced infrastructure and services to ensure that Warmley is not overwhelmed.
2025-2028
- Outline planning application submitted in Summer 2025. Â
- Adoption of the South Gloucestershire Local Plan. Â
- Outline application determined by South Gloucestershire Council Planning Committee.Â
- Outline consent granted, and Section 106 payments agreed with South Gloucestershire Council. Â
- Warmley Design Code created.Â
- First Reserved Matters application submitted.Â
- Reserved matters consent granted.Â
2029-2031
- Housing construction and road infrastructure work begins. Â
- Warmley Forest Park extension completed, including pedestrian and cycle path through the park.Â
- Approximately 50 homes built in the first year.Â
- Site access points at London Road and Webbs Heath (North West) created. Â
- Pedestrian and cycle path delivered, linking the site to the Bristol and Bath Railway Path at Warmley railway station. Â
- Mobility hub delivered. Â
- Land prepared for construction of the local centre and elderly persons care home.Â
- North-South road through the site completed, connecting Webbs Heath to London Road.Â
- Approximately 210 homes delivered by end of 2031. Â
2032-2039
- Up to 100 homes per year are constructed
- Completion of local centre and care home.Â
- All homes at North Warmley and all wildlife enhancements delivered by Winter 2039. Â